Louisiana Superdome!
New Orleans, LA
All Star is proud to be involved in development of our hometown icon, The
Louisiana Superdome.
Phase 1The first phase of
the project consisted of relocation of the press box/press area from the 300
level to the 700 level. This initialed building new seating with power and
data outlets along with relocation the audio and video controls from the 300
level to the new press box. Also included in phase 1 was the build out of 13
new luxury suites on the 300 level. This project was on a fast track
schedule and had to be completed in 4 months. We also totally remodeled the
World Champion New Orleans Saints locker room. This locker room was
completely gutted and rebuild into a state of the art facility that will
handle the Saints need for many years.
Phase 2
The second phase consists of a total remake on the 100 plaza level and along
with concession areas and bathrooms. This project includes expanding the
plaza concourse by 30’ and adding new food venders as well as badly needed
bathrooms. The 100 level seating along the sidelines will be removed and
replaced with permanent seating. Under the new permanent seating we are
installing 2- new floor level “Bunker Clubs. These clubs are used to
entertain fan during the pregame festivities. The Bunker clubs along with
the Plaza level work did require a substantial service upgrade along with a
large electrical build-out.
Champion Square
Champion Square was built on the site of the old New Orleans Centre. This
project consisted of installing a 2 million dollar Audio/Video entertainment
system for fans during the pregame activates. A series of electrical panels
and circuits were installed to supply power to the theatrical equipment
along with food vender equipment.
[